Water tank, Southport UK

Project facts

Description Water tank, Southport
Challenge Three large wastewater tanks to be constructed in just 12 weeks

Client United Utilities required three large wastewater tanks to be constructed in just 12 weeks to maintain their fast-track project programme. The 9.4 m high tanks with diameters of up 42 m are part of a storm water retention scheme at the plant.

Hünnebeck (Formerly Harsco Infrastructure) designed and supplied a high-productivity formwork solution using the LOGIK® 360 circular panel formwork system. These panels can be adjusted on site to suite the radius required then installed and reused like a conventional wall panel system. This solution allowed pours to take place at a rate of up to one a day. The panels were re-adjusted for each tank with pours taking place in two lifts - the first to a height of 4.8 m and the second taking the overall height to 9.4 m.