Waste water treatment plant, Ashton UK

Project facts

Description Waste water treatment plant, Ashton
Challenge Challenging construction deadline

To help to meet a challenging construction deadline, Hünnebeck's (Formerly Harsco Infrastructure) LOGIK® 60 large area formwork panel system was specified for the construction of a wastewater treatment works in Ashton under Lyne, Greater Manchester.

The heavy-duty LOGIK® 60 panels were linked together to form wall panels over 7 m tall. These were then craned in to position for the construction of the activated sludge tank. The walls were poured in lengths of up to 40 m long. The LOGIK system allowed these large panel assemblies to be crane lifted without additional bracing or walers. Formwork erection and dismantling on the various stages of the structure is therefore extremely quick.